Pursat Hydropower Dam Nears Completion, Set to Start Generating Power and Easing Floods by Year-End

The 80-megawatt Stung Pursat 1 hydropower plant in Veal Veng district, Pursat province, is nearly finished and is scheduled to begin producing electricity in December. Its developer says the dam can also help lessen downstream flooding and supply water for farms during the dry months.
The site is in Stung Thmei village, Pramaoy commune, about 75 kilometres from Pursat town. South Korean firm SPHP (Cambodia) Co., Ltd. is developing the project, which broke ground in 2021.
On October 23, the project's managing director, Hong Soo Young, led journalists on a tour of the facility. He said the main structures are in their final construction phase and that the dam's gates have been closed, allowing the reservoir to start filling.
Construction is now more than 90 percent complete, Hong said through an interpreter. Power generation is expected to start in December 2026, but full output of 80MW may not arrive until the following year, since the reservoir still needs time to fill enough for full-scale operation.
Hong explained that river flows rise and fall with the seasons, but the dam's large storage capacity is designed to let it generate power all year rather than relying solely on the natural flow of the river.
Project specifications
- Total installed capacity of 80MW, split across two identical generating units
- Reservoir storage of about 1.2265 billion cubic metres, including roughly 999 million cubic metres for regulating flow
- Infrastructure including a spillway, water conveyance structures, a powerhouse, a switchyard and a 230-kilovolt transmission line
- Dam measuring roughly 100 metres high and 680 metres wide, with a seven-metre-wide road along its crest for future site access
- Turbine discharge of up to about 3.5 million cubic metres per day under optimal conditions
Flood control and farming benefits
Beyond electricity, Hong pointed to the reservoir's ability to hold back water upstream during heavy rain. Rather than sending a surge of runoff toward Pursat town all at once, the reservoir can capture a large share of it, which could reduce flood pressure on downstream communities. He did not estimate how much flooding could be reduced or which areas would benefit most.
During the dry season, stored water can drive the turbines, and the water released through them can also support farming downstream.
Construction challenges and investment
Hong acknowledged that building the dam over several years has been difficult, particularly during the rainy season, when heavy downpours and slick ground slowed work. Progress was generally smoother in the dry season.
He put the project's cost at roughly $250 million, although earlier figures given to reporters had indicated an investment of around $231 million. The company is financing construction under a 35-year investment agreement, after which the entire facility will be handed over to the Cambodian government. Hong credited the government with supporting investment conditions, land arrangements and the paperwork needed for the project. He said the company had compensated residents whose land or property was affected, in coordination with authorities, but did not disclose how many households were involved or the total amount paid.
According to the company's schedule, construction should be finished by December 31, 2026, with electricity generation beginning that same month, adding a new domestic source to Cambodia's power network. How well the dam manages floods and supplies irrigation will depend on how the reservoir is operated, local hydrological conditions, and the water distribution infrastructure serving downstream areas.